Terms & Conditions:-
Price:-
· Quoted prices are applicable for this proposal only, any modifications may result in a change of prices.
· The quoted rates are an estimate based on current design and sizes.
· Designs are liable to change till the sign off the design phase.
· Depending on the exact actual measurements on the site prices may change.
· Deep cleaning for your home post-handover can be provided by Asense at an extra cost as below:
·
» 2bhk = Rs. 7500 + taxes. |
» 3bhk = Rs. 9000 + taxes. |
» >3bhk = @ 8Rs. per sft on SBA. |
·
·
· Floor covering of your existing flat will be charged extra at Rs. 8 per sft/ this will be done by default by Asense added to your bill at the time of going to production as per actual site measurements.
· Painting and light suggestion will only be given if you book the same services with us.
· High Quality 3D Render services can be provided by Asense on extra cost.
· If service lift isn’t operational then uplifting charges of 10000 rs. will be applicable till 5th floor. Beyond that as per floor count charges will be applicable.
· Any lamination beyond the price of 1000 rs/sheet. will be charged extra.
· Soft closer hinz & channel will be charged extra.
· Any extra accessories, Carcass top, lights, electrical materials, Point shifting or any other extra work will be charged as per actual.
· Based on Design Rates May differ for each and every Unit.
· PVC Sheet, Veneer, Digital Lamination, Lacquer Glass and Acrylic sheet will be charged extra as per the actual rate.
· All kind profile handle, Profile shutter cost will be charged extra.
· Extra Drawer/Basket Or any other accessories will be charged extra as per actual.
· Time of installation all the internal house wall may get some damages and for that you need to do one coat of painting after completion of woodwork.
· Asense is able to process your final order and start production only post a 55% payment, Key and work permission letter.
Below work can be done at extra cost:-
·
· Civil work (Breaking existing partitions, walls or counters making)
· Plumbing material & services
· Electrical points shifting
· Electrical Appliances and/or installation
· Chimney installation & ducting
· Wall tiles and installation
· Cornice / Moldings & Pelmet
· Kitchen & Cabinet Spotlights
· Hanging accessories
· Copper gas pipe and installation
· False Ceiling and Furniture lights
· Stone Work
· Wall Core Cutting
· Deep Cleaning
Production & Installation Schedule:-
Project Value |
Buffer time in-between after design finalization to start the Production |
Total Project Timeline till handover for estimated work |
Painting & other works |
6-8 lac |
7 working days |
45 working Days |
8-10 working Days |
8-12 lac |
7 working days |
55 working Days |
10-12 working Days |
12-15 lac |
7 working days |
65 working Days |
15-17 working Days |
15-20 lac |
7 working days |
75 working Days |
18-20 working days |
20-25 lac |
7 working days |
85 working Days |
25 working days |
*Asense will keep 15 working days of buffer time for unconditional foreseen situations.
*Asense won’t be responsible for any delay in project implementation due to third party vendors or for reasons beyond its control.